Platinum User

University of Minnesota

General Overview

Smith Hall Roof Renovation Project, 2006

In 2005, the University of Minnesota Capital Planning and Project Management (CPPM) partnered with the PBSRG to test the PIPS Best-Value process on various construction projects on the Twin Cities Campus. The goal of the research was to increase the performance of construction, obtain the best-value for the University, and increase the overall efficiency of the delivery of construction. The process was initially tested on roofing, mechanical, and electrical projects.

In 2007, after two years of testing, UMN-CPPM made the PIPS program a standard procurement option available on all projects. This decision was made in part due to the high performance results of the pilot program. In 2008, the UMN-CPPM expanded the use of the program to include professional services (architectural, engineering, and consulting).

In 2011, Michael Perkins stated on an NCS Radio interview that while using PIPS, the University has saved $42M or 31% off their expected spend in construction projects.

You can now download the November 1, 2011 PIPS training slides.

Minnesota General Information


Program Summary & Significant Achievements (Updated 11/1/2011)

# Criteria Results
Number of years using/testing PIPS 6 Years
Total number of project procured using PIPS 306
Total size of projects $221.4 M
Total number of vendors with Past Performance Information (PPI) 351
Total number of completed projects 213
Percent of project completed without vendor cost increases 99%
Average contractor change order rate 0.1%
Final post project close out rating of PIPS (1-10) 9.6
Final post project close out rating of vendor (1-10) 9.5
Average increase in contractor profit 4.5%
Percent of projects where Best Value was also lowest cost 51%

Best Value Projects

Past Performance Information

Past Performance Information (PPI) is used to assist the client in selecting a high performing team for a particular project. PPI is collected on construction firms, design firms, and critical project individuals.

# Description
UMN List of Contractors with PPI
UMN-PPI-Scores (Updated 01/25/2012)
Survey Form & Guide to Preparing PPI – Contractors
Survey Form & Guide to Preparing PPI – Architects, Engineers
Survey Form & Guide to Preparing PPI – Consultants
Survey Form & Guide to Preparing PPI – Roofing
Reference List Template - A & E
Reference List Template - Roofing
Reference List Template - Construction
PPI Code Request (to view your PPI score)

Please email a completed copy of the Reference List (XLS file) and scanned PDF of surveys to pips@umn.edu

Video Tutorials

  1. Pre Award Phase Tutorial - 20 Min
  2. Weekly Risk Reporting System Tutorial - 20 Min

* These videos are only available to CPPM clients and qualified vendors.