Pre-Planning Enables Facility Optimization

,

Cost Savings: 35%
Schedule: 60% reduction

Contractor Change Orders: 0%

Type: Design Build Construction

Contractor: Stuart Olson Dominion Construction, LLC

Location: Edmonton, Canada

 

Contract: $21,000,000

 

Start Date: October 2011

Completion Date: December 2012

Design Build for High Tech Research Space

The University of Alberta redeveloped existing research space into a hot lab with a cyclotron particle accelerator. For this extremely complex project, the University used the Best Value Model for selection, pre-planning, and performance measurement.

The Best Value pre-planning process resulted in significant savings and optimization of facility operation.  As a result of the pre-planning process, the contractor identified & minimized unforeseen design and constructability risks before the project began.

“Best Value saved 14-18 months in schedule and $8-12M in cost when compared with traditional processes that would have resulted in change orders during construction” – Hugh Warren, Dir. Facilities & Operations

Using Best Value IPD, the project will be completed in approximately 18 months at $28M, whereas owner estimates of using a traditional delivery model would place the project at 48 months and $44 – 48M.

REFERENCE: Hugh Warren, Executive Director of Operations & Maintenance | hugh.warren@ualberta.ca | 780-492-6405