Project Overview
The project includes the installation of supply and return piping from the existing stub-ins in the fleet garage to the heat pump room. Four (4) pumps, a heat exchanger and two (2) three-way control valves are to be installed in the heat pump room. Four main piping headers and 28 three-way control valves are to be installed in the mezzanine area above the heat pump room. Piping to connect the heat pumps to the headers and the three-way valves on the mezzanine is also required.
Schedule
| NO | End Date | Task |
| 1 | 11/22/2010 | Project Announcement |
| 2 | 12/06/2010 | Pre-Proposal/Education Meeting |
| 3 | 12/22/2010 | Submittals Due |
| 4 | 12/29/2010 | Potential Best-Value Firm Notification |
| 5 | 01/05/2011 | Pre Award Kickoff Meeting |
| 6 | 01/21/2011 | Pre-Award meeting |
| 7 | 01/25/2011 | Board Award |
Bidding / Proposal Information