Project Overview

The project consists of ventilation systems replacement, fire alarm replacement, elevator replacement, restroom upgrades, and other misc. improvements.

Schedule

# End Date Task
11/10/09 Pre Bid Meeting & Site Visit at 2:45pm
12/3/09 Proposals Due
12/8/09 Notification of Shortlist
12/10/09 Interviews
12/11/09 Identification of Potential Best Value
12/15/09 Pre-Award Meeting
1/9/10 Board Meeting
1/20/10 Notice to Proceed Date
6/14/10 Construction Start Date
8/27/10 Final Completion Date

Award Information

Vendor Name: GC- Knutson Construction, Mech - HiMec Mechanical
Elec - Nietz Electric
Estimated Budget: $1,800,000
Awarded Cost: GC - $643,000, Mech - $1,844,000
Elec - $236,000
Awarded Duration: GC- 205 days, Mech- 218 days
Elec- 212 days
Detailed Award Info: John Adams Middle School Phase II Award Info
Project Risks: John Adams Middle School Phase II Risks