John Adams Middle School Phase II Renovation
Project Overview
The project consists of ventilation systems replacement, fire alarm replacement, elevator replacement, restroom upgrades, and other misc. improvements.
Schedule
| # | End Date | Task |
| 11/10/09 | Pre Bid Meeting & Site Visit at 2:45pm | |
| 12/3/09 | Proposals Due | |
| 12/8/09 | Notification of Shortlist | |
| 12/10/09 | Interviews | |
| 12/11/09 | Identification of Potential Best Value | |
| 12/15/09 | Pre-Award Meeting | |
| 1/9/10 | Board Meeting | |
| 1/20/10 | Notice to Proceed Date | |
| 6/14/10 | Construction Start Date | |
| 8/27/10 | Final Completion Date |
Award Information
| Vendor Name: | GC- Knutson Construction, Mech - HiMec Mechanical Elec - Nietz Electric |
| Estimated Budget: | $1,800,000 |
| Awarded Cost: | GC - $643,000, Mech - $1,844,000 Elec - $236,000 |
| Awarded Duration: | GC- 205 days, Mech- 218 days Elec- 212 days |
| Detailed Award Info: | John Adams Middle School Phase II Award Info |
| Project Risks: | John Adams Middle School Phase II Risks |