Project Overview

The project consists of ventilation systems replacement, fire alarm replacement, elevator replacement, restroom upgrades, and other misc. improvements.

Schedule

# End Date Task
3/24/09 Pre Bid Meeting & Site Visit at 1:00pm
4/3/09 Proposals Due
4/6/09 Notification of Shortlist
4/8/09 Interviews
4/9/09 Identification of Potential Best Value
4/15/09 Pre-Award Meeting
4/21/09 Board Meeting
4/22/09 Notice to Proceed Date
6/15/09 Construction Start Date
8/28/09 Final Completion Date

Award Information

Vendor Name: GC - Alvin E. Benike, Inc
Elec - Ryan Electric, Mech - DMC Plumbing and Heating, Inc.
Estimated Budget: $1.8 Million
Awarded Cost: GC- $393,595
Elec - $121,575 Mech - $831,000
Awarded Duration: GC- 123 Days
Elec - 67 Days Mech - 122 Days
Detailed Award Info: John Adams Middle School Phase I Award Info
Project Risks John Adams Middle School Phase I Risks

Closeout Status

Vendor met proposed schedule:
Yes
Vendor met proposed cost:
Yes
Vendor met purposed quality/customer satisfaction:
Yes
Final customer rating of PIPS (10 max):
10
Final rating of contractor (10 max): 10