The project consists of ventilation systems replacement, fire alarm replacement, elevator replacement, restroom upgrades, and other misc. improvements.
Schedule
| # | End Date | Task |
| 3/24/09 | Pre Bid Meeting & Site Visit at 1:00pm | |
| 4/3/09 | Proposals Due | |
| 4/6/09 | Notification of Shortlist | |
| 4/8/09 | Interviews | |
| 4/9/09 | Identification of Potential Best Value | |
| 4/15/09 | Pre-Award Meeting | |
| 4/21/09 | Board Meeting | |
| 4/22/09 | Notice to Proceed Date | |
| 6/15/09 | Construction Start Date | |
| 8/28/09 | Final Completion Date |
Award Information
| Vendor Name: | GC - Alvin E. Benike, Inc Elec - Ryan Electric, Mech - DMC Plumbing and Heating, Inc. |
| Estimated Budget: | $1.8 Million |
| Awarded Cost: | GC- $393,595 Elec - $121,575 Mech - $831,000 |
| Awarded Duration: | GC- 123 Days Elec - 67 Days Mech - 122 Days |
| Detailed Award Info: | John Adams Middle School Phase I Award Info |
| Project Risks | John Adams Middle School Phase I Risks |
Closeout Status
|
Vendor met proposed schedule:
|
Yes |
|
Vendor met proposed cost:
|
Yes |
|
Vendor met purposed quality/customer satisfaction:
|
Yes |
|
Final customer rating of PIPS (10 max):
|
10 |
| Final rating of contractor (10 max): | 10 |