Saddle Creek Fire Rescue Station
Project Overview
Scope of work includes, but is not limited to, all labor, equipment, materials, supplies, and supervision necessary to construct the fire rescue stations inclusive of all site work, building, and required utility infrastructure as contained within the attached Technical Specifications and drawings.
Schedule (*Updated July 7, 2010)
| NO | End Date | Task |
| 1 | 06/02/10 | Project Announcement |
| 2 | 06/16/10 | Mandatory Pre Submittal Conference & Mandatory Site Visit, 9:00AM
(*see Section 1.4 for details) |
| 3 | 06/25/10 | Deadline for Questions [1:00PM] Eastern Time Zone |
| 4 | 07/21/10 | Best Value Submittals due prior to [2:00 PM] Eastern Time Zone |
| 5 | 08/06/10 | Notification of Shortlisted Finalist (If Applicable) |
| 6 | 08/13/10 | Interview of Shortlisted Finalist (If Applicable) |
| 7 | 08/20/10 | Identification of Potential Best Value |
| 8 | 08/27/10 | Kick Off Meeting |
| 9 | 09/27/10 | Pre Award Meeting |
| 10 | 10/20/10 | Anticipated Date of Award / Notice to Proceed |