Rochester National Volleyball Court Expansion

Project Overview

This project consists of an addition to the existing National Volleyball Center including new courts, restrooms, office, and storage areas. A description of the major work elements and assemblies is as follows: site pavements and ground covers; concrete frost depth foundations with a concrete slab on grade floor structure; steel structure frame with masonry cavity wall and precast architectural wall panel enclosures, bar joist/steel roof deck with membrane roof covering system; interior fit-up and finishing; extension of existing heating and cooling system, new air handling unit and ventilation systems; plumbing systems; fire protection systems; electrical power systems; and internal and external lighting.

Schedule

# End Date Task
02/14/11 Project Announcement
02/21/11 RFP Released
03/03/11 Pre-Proposal Meeting (MANDATORY)
03/03/11 Educational Meeting (MANDATORY)
03/09/11 Last Day for Questions
03/16/11 Proposals Due (11:00AM Minnesota Time)
03/24/11 Interviews
03/24/11 Identification of Potential Best-Value
03/25/11 Pre Award Kick Off Meeting
04/14/11 Final Pre Award Meeting
04/19/11 Project Award
01/13/12 Anticipated Substantial Completion Date

Award Information

Vendor Name: Alvin E. Benike, Inc.
Estimated Budget: $3,400,000
Awarded Cost: $3,051,800
Awarded Duration: 273 Days
Scope of Work: Volleyball Center Expansion
Detailed Award Info: Rochester NVC - Award Info
Project Risks: Rochester NVC - Risks