Rochester National Volleyball Court Expansion
Project Overview
This project consists of an addition to the existing National Volleyball Center including new courts, restrooms, office, and storage areas. A description of the major work elements and assemblies is as follows: site pavements and ground covers; concrete frost depth foundations with a concrete slab on grade floor structure; steel structure frame with masonry cavity wall and precast architectural wall panel enclosures, bar joist/steel roof deck with membrane roof covering system; interior fit-up and finishing; extension of existing heating and cooling system, new air handling unit and ventilation systems; plumbing systems; fire protection systems; electrical power systems; and internal and external lighting.
Schedule
| # | End Date | Task |
| 02/14/11 | Project Announcement | |
| 02/21/11 | RFP Released | |
| 03/03/11 | Pre-Proposal Meeting (MANDATORY) | |
| 03/03/11 | Educational Meeting (MANDATORY) | |
| 03/09/11 | Last Day for Questions | |
| 03/16/11 | Proposals Due (11:00AM Minnesota Time) | |
| 03/24/11 | Interviews | |
| 03/24/11 | Identification of Potential Best-Value | |
| 03/25/11 | Pre Award Kick Off Meeting | |
| 04/14/11 | Final Pre Award Meeting | |
| 04/19/11 | Project Award | |
| 01/13/12 | Anticipated Substantial Completion Date |
Award Information
| Vendor Name: | Alvin E. Benike, Inc. |
| Estimated Budget: | $3,400,000 |
| Awarded Cost: | $3,051,800 |
| Awarded Duration: | 273 Days |
| Scope of Work: | Volleyball Center Expansion |
| Detailed Award Info: | |
| Project Risks: |