City of Rochester's first PIPS process is the construction of a new Public Works and Transit Operations Center in northeast Rochester. This project consists of a main operations building with offices, a fleet parking garage, adjacent vehicle repair bays, workshops, and storage areas. Separate structures for wash and fuel operations, equipment storage and material storage along with all site pavements and ground covers.
Schedule
| # | END DATE | TASK |
| 12/14/09 | Project Announcement | |
| 1/05/10 | Site Tour | |
| 1/21/10 | Proposals due | |
| 2/02/10 | Interviews | |
| 2/03/10 | Kick-Off meeting | |
| 3/09/10 | Pre-Award Meeting | |
| 3/17/10 | Anticipated Notice to Proceed Date | |
| 04/2010 | Construction Start Date | |
| 06/2011 | Final Completion Date |
Award Information
| Vendor Name: | Alvin E. Benike, Inc. |
| Estimated Budget: | $28.5 Million |
| Awarded Cost: | $22,675,162 |
| Awarded Duration: | 441 days |
| Scope of Work: | New construction of Public Works and Transit Operations. |
| Detailed Award Info: | Public Works & Transit Operations Award Information |
| Project Risks | Public Works & Transit Operations Project Risks |
Photos of the Project