Project Overview
Complete construction of the ELECTRICAL TECHNOLOGY PACKAGE at the new Public Works and Transit Operations Center. This project consists of a main operations building with offices, a fleet parking garage, adjacent vehicle repair bays, workshops, and storage areas. Additional work associated with separate on site structures for wash and fuel operations, equipment and material storage, and site improvements.
Major Work: “Voice Data/ Video Structured cabling systems, paging and Intercom System, CATV Cabling system and Security System”.
Schedule
| # | End Date | Task |
| 06/08/2010 | Pre Proposal/ Best Value Trainning (Mandatory) | |
| 06/23/2010 | Submittals Due | |
| 06/29/2010 | Notification of Shortlist | |
| 06/30/2010 | Interviews (if conducted) | |
| 07/01/2010 | Pre-Award Kickoff Meeting | |
| 07/26/2010 | Final Pre-Award Meeting | |
| 08/02/2010 | Project Award |
Award Information
| Vendor Name: | All Systems Installation, Inc. |
| Estimated Budget: | $400,000 |
| Awarded Cost: | $357,325 |
| Awarded Duration: | 150 Days |
| Scope of Work: | Electrical Technology Package |
| Detailed Award Info: | |
| Project Risks: |