Project Overview

Arizona State Parks is requesting proposals from qualified Design-Build firms for professional services at Slide Rock State Park, 6871 N. Highway 89A, Sedona, Arizona 86336 for design, construction, and demolition in compliance with existing regulations as follows:

  1. Design & build a new waste water Treatment Plant to serve the present & future needs of the Park.
  2. Design & build two identical new Restroom Buildings to facilitate 2,500 Park visitors per day.
  3. Design & build one new stock pre-engineered Maintenance Building to facilitate maintenance & storage needs.
  4. Design & build water, sewer, & electrical utility lines with all necessary appurtenances to ensure a fully functional project.
  5. Demolition of an existing Clivus-Multrum facility with adjacent Effluent Treatment Bed (ETB).

Schedule

# End Date Task
4/02/08 Pre-Proposal/Educational Meeting
4/03/08 Pre-Proposal Site Visit
5/01/08 Proposers Submit Reference Lists
5/01/08 Surveys Due
5/01/08 Proposals and Risk Assessment & Value Added Plans Due
5/07/08 Interviews
5/08/08 Identification of Potential Best Value
5/14/08 Pre-planning Kickoff Meeting
6/04/08 Preplanning and Quality Control Meeting
6/18/08 Award

Bidding / Proposal Information

All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.

Award Information


Vendor Name: Fann Environmental, LLC
Estimated Budget: $1,200,000
Awarded Cost: $1,697,243
Awarded Duration: 617 Days