« Back to Arizona State Parks

Picacho Peak State Park

Project Overview

Construction Manager at Risk to construct New LEED certified Visitor Center at Picacho Peak State Park, I-10 Exit 219, Picacho, Arizona 85241.

Schedule

# End Date Task
05/20/08 Pre-Proposal Educational Meeting
05/22/08 Pre-Proposal Site Visit
06/06/08 Proposers Submit Reference Lists
06/06/08 Proposers Surveys Due
06/06/08 Proposals, Risk Assessment & Value Added Plans Due
06/17/08 Interviews
06/17/08 Identification of Potential Best Value
06/23/08 Pre-Planning Kickoff Meeting
07/09/08 Pre-Planning and Quality Control Meeting
07/22/08 Award
07/23/08 Notice To Proceed
10/15/08 Park Ingress and Egress Availability
01/15/09 Total and Final Completion

Bidding / Proposal Information

All information is removed once bids are submitted. To obtain this information, please contact the client or the PBSRG.

Award Information


Vendor Name: Concord General Contracting
Estimated Budget: $950,000
Awarded Cost: $1,258,000
Awarded Duration: 177 Days